DAILY DIVE LOG REPORT
PT. Uma Offshore Teknologi | Report Diving Operation
General Info
Date:
8 December 2025
Location:
SWI Jetty
Client:
PT. Mcconnel Dowel Indonesia
Job No:
08/MBBI-MCDI/XII/2025
Dive No:
08B/MBBI-MCDI/XII/2025
Task / Activity:
Underwater lifting and cutting to favilitate metal debris lifting.
Personnel
Dive Supervisor:
Ahmad Maulana
Diver:
Imam
Standby Diver:
Yakub
Tender 1:
Natas
Tender 2:
Environmental Conditions
Weather:
Clear
Wind Speed:
0-5 Knots
Wave Height:
m
Current:
Moderate
Water Temp:
29 °C
Depth:
23 ft
Dive Timing
Left Surface:
14:31
Arrive Bottom:
14:32
Left Bottom:
16:25
Arrive Surface:
16:26
Bottom Time:
113 min
Total Time:
115 min
Summary
Job Result:
The diver perform underwater airlifting and cutting. One hollow can be lifted
Signed by:
Ahmad Maulana