DAILY DIVE LOG REPORT

PT. Uma Offshore Teknologi | Report Diving Operation

General Info
Date:8 December 2025
Location:SWI Jetty
Client:PT. Mcconnel Dowel Indonesia
Job No:08/MBBI-MCDI/XII/2025
Dive No:08B/MBBI-MCDI/XII/2025
Task / Activity:Underwater lifting and cutting to favilitate metal debris lifting.
Personnel
Dive Supervisor:Ahmad Maulana
Diver:Imam
Standby Diver:Yakub
Tender 1:Natas
Tender 2:
Environmental Conditions
Weather:Clear
Wind Speed:0-5 Knots
Wave Height: m
Current:Moderate
Water Temp:29 °C
Depth:23 ft
Dive Timing
Left Surface:14:31
Arrive Bottom:14:32
Left Bottom:16:25
Arrive Surface:16:26
Bottom Time:113 min
Total Time:115 min
Summary
Job Result:The diver perform underwater airlifting and cutting. One hollow can be lifted
Supervisor Signature

Signed by: Ahmad Maulana

Foto Dokumentasi