DAILY DIVE LOG REPORT
PT. Uma Offshore Teknologi | Report Diving Operation
General Info
Date:
30 November 2025
Location:
SWI Jetty
Client:
PT. Mcconnel Dowel Indonesia
Job No:
30/MBBI-MCDI/XI/2025
Dive No:
30A/MBBI-MCDI/XI/2025
Task / Activity:
Underwater inspection and cutting operations to facilitate the lifting process.
Personnel
Dive Supervisor:
Ahmad Maulana
Diver:
Imam
Standby Diver:
Yakub
Tender 1:
Natas
Tender 2:
Environmental Conditions
Weather:
Cloudy
Wind Speed:
0-5 Knots
Wave Height:
0.5 m
Current:
Moderate to Strong
Water Temp:
30 °C
Depth:
23 ft
Dive Timing
Left Surface:
10:09
Arrive Bottom:
10:10
Left Bottom:
11:38
Arrive Surface:
11:39
Bottom Time:
88 min
Total Time:
90 min
Summary
Job Result:
The diver has perform underwater inspection and cutting operations to facilitate the lifting process.
Signed by:
Ahmad Maulana