PT. Uma Offshore Teknologi | Report Diving Operation
General Info
Date:26 November 2025
Location:SWI Jetty
Client:PT. Mcconnel Dowel Indonesia
Job No:26/MBBI-MCDI/XI/2025
Dive No:26A/MBBI-MCDI/XI/2025
Task / Activity:Connect sling crane to metal for be lifted.
Personnel
Dive Supervisor:Ahmad Maulana
Diver:Natas
Standby Diver:Imam
Tender 1:Yakub
Tender 2:
Environmental Conditions
Weather:Clear
Wind Speed:0-5 Knots
Wave Height:0.5 m
Current:Moderate
Water Temp:30 °C
Depth:23 ft
Dive Timing
Left Surface:13:57
Arrive Bottom:13:58
Left Bottom:16:47
Arrive Surface:16:48
Bottom Time:169 min
Total Time:171 min
Summary
Job Result:The diver successfully connected the sling to the four metal debris and cut the remaining attached sheet piles, allowing all four materials to be lifted using the crane.