DAILY DIVE LOG REPORT
PT. Uma Offshore Teknologi | Report Diving Operation
General Info
Date:
25 November 2025
Location:
SWI Jetty
Client:
PT. Mcconnel Dowel Indonesia
Job No:
25/MBBI-MCDI/XI/2025
Dive No:
25B/MBBI-MCDI/XI/2025
Task / Activity:
Continue Underwater cutting metal debris.
Personnel
Dive Supervisor:
Ahmad Maulana
Diver:
Natas
Standby Diver:
Imam
Tender 1:
Yakub
Tender 2:
Environmental Conditions
Weather:
Clear
Wind Speed:
0-5 Knots
Wave Height:
0.5 m
Current:
Moderate
Water Temp:
30 °C
Depth:
23 ft
Dive Timing
Left Surface:
14:22
Arrive Bottom:
14:23
Left Bottom:
15:49
Arrive Surface:
15:50
Bottom Time:
86 min
Total Time:
88 min
Summary
Job Result:
The diver finish cutting debris.
Signed by:
Ahmad Maulana