DAILY DIVE LOG REPORT

PT. Uma Offshore Teknologi | Report Diving Operation

General Info
Date:23 November 2025
Location:SWI Jetty
Client:PT. Mcconnel Dowel Indonesia
Job No:23/MBBI-MCDI/XI/2025
Dive No:23B/MBBI-MCDI/XI/2025
Task / Activity:Continue Underwater cutting metal debris.
Personnel
Dive Supervisor:Ahmad Maulana
Diver:Yakub
Standby Diver:Natas
Tender 1:Imam
Tender 2:
Environmental Conditions
Weather:Cloudy
Wind Speed:0-5 Knots
Wave Height:0.5 m
Current:Moderate
Water Temp:29 °C
Depth:23 ft
Dive Timing
Left Surface:14:05
Arrive Bottom:14:06
Left Bottom:16:07
Arrive Surface:16:08
Bottom Time:121 min
Total Time:123 min
Summary
Job Result:The diver has finished cutting the sheet piles to be lifted.
Supervisor Signature

Signed by: Ahmad Maulana