DAILY DIVE LOG REPORT
PT. Uma Offshore Teknologi | Report Diving Operation
General Info
Date:
22 November 2025
Location:
SWI Jetty
Client:
PT. Mcconnel Dowel Indonesia
Job No:
22/MBBI-MCDI/XI/2025
Dive No:
22B/MBBI-MCDI/XI/2025
Task / Activity:
Underwater cutting metal debris on seabed.
Personnel
Dive Supervisor:
Ahmad Maulana
Diver:
Natas
Standby Diver:
Imam
Tender 1:
Yakub
Tender 2:
Environmental Conditions
Weather:
Cloudy
Wind Speed:
0-5 Knots
Wave Height:
0.7 m
Current:
Moderate to Strong
Water Temp:
30 °C
Depth:
23 ft
Dive Timing
Left Surface:
14:34
Arrive Bottom:
14:35
Left Bottom:
16:18
Arrive Surface:
16:19
Bottom Time:
103 min
Total Time:
105 min
Summary
Job Result:
Underwater cutting metal debris on seabed cannot continue because heavy rainy.
Signed by:
Ahmad Maulana