Company Logo

DAILY DIVE LOG REPORT

PT. Uma Offshore Teknologi | Report Diving Operation

General Info
Date:13 November 2025
Location:SWI Jetty
Client:PT. Mcconnel Dowel Indonesia
Job No:13/MBBI-MCDI/XI/2025
Dive No:13A/MBBI-MCDI/XI/2025
Task / Activity:Underwater inspection and cutting of metal debris to facilitate easier lifting first.
Personnel
Dive Supervisor:Ahmad Maulana
Diver:Imam
Standby Diver:Yakub
Tender 1:Bambang
Tender 2:
Environmental Conditions
Weather:Clear
Wind Speed:0-5 Knots
Wave Height:0.5 m
Current:Moderate
Water Temp:29 °C
Depth:20 ft
Dive Timing
Left Surface:08:35
Arrive Bottom:08:36
Left Bottom:09:57
Arrive Surface:09:58
Bottom Time:81 min
Total Time:83 min
Summary
Job Result:The metal debris has been cut using a Broco torch, but the cutting is still insufficient for lifting. Many parts remain interconnected, which prevents recovery operations from proceeding until additional dredging is carried out.
Supervisor Signature

Signed by: Ahmad Maulana

Foto Dokumentasi